December 2017 - Sales Contract signed
February 2018 - Tender Appointment Completed ( Structural Elements Finalized)
May 2018 - Contract signed (Expected)
June 2018 - House Demolition (Expected)
August 2018 - Build Start Date (Expected)
- January 2018 - Soil & Site Survey Completed.
February 2018 - Tender Appointment Completed ( Structural Elements Finalized)
- February - March 2018 - Spent 2-3 hours a week at world of style deciding on various Fittings.
April 2018 - World of Style Appointments. ( Non-Structural Elements Finalized)
May 2018 - Contract signed (Expected)
June 2018 - House Demolition (Expected)
August 2018 - Build Start Date (Expected)